Initial Land Deposit 06/02/2013
Initial House Deposit 24/02/2013
Contour Survey 14/03/2013
Soil Report 18/03/2013
Tender Appointment 22/03/2013
Tender Signed 10/04/2013
Land Settlement 01/05/2013
Building Contract Appointment 02/05/2013
Building Contract Signed 02/05/2013
Colour Selection 08/05/2013
BASIX Approval 13/05/2013
Engineering Drawings Signed 20/05/2013
Council Permit Ordered 31/05/2013
Water Board Approval 13/06/2013
Kitchen Upgrades 19/06/2013
Electrical Selection 19/07/2013
Council Permit Received 24/07/2013
Construction Drawings Signed 03/09/2013
Construction Certificate 04/09/2013
Administration Complete