Tuesday 29 October 2013

Frames are up!

Visited the site on Monday morning. Frames were up as well as windows/sliding doors and plumbing which all seemed to be completed. 

Bricks were supposed to be delivered on Friday but found out that roof will be done this week instead of bricks. Brick delivery scheduled for this Friday 1/11.

Some pics:








Frame Delivery

Some pics from frame delivery






Monday 14 October 2013

First invoice

SS called and left a voicemail yesterday...

Apparently plumbing / drainage guys will be completing their work today. Frames are due to be started on Wed/Thu this week.

In the meantime first invoice for the slab came through via email last Friday and in the mail today. Amazing how quick they come through! I Will be faxing the authority form to the Bank today. Hopeful the drawdown doesn't take long so that it doesn't delay any work...

The nice weather continues, hopefully it stays this way :)

Thursday 10 October 2013

Slabbed :)

Visited the site today since SS had advised that the slab would be poured on Wed/Thu. Got to my site around 6ish in the evening since I was allowed to knock off work a little early. It was an extremely hot day today...39 degrees! :)

I found the base of our new home starting to cure...here are some pics.