Visited the site over the weekend and it was good too see that some work had been done.
Most of the paintwork seems to be completed now. The house looks much more fresh and bright, whereas before the paintwork it looked quite dull. We visited around 6pm and it looked pretty bright now even at that time of the day.
Internal works:
- All internal doors painted
- All walls painted
- Front door painted/stained
External works:
- Downpipes painted (dark Monument)
- Eaves painted (paperbark)
- Front maroka seems completed (Paperbark colour on bricks)
- Alfresco ceiling and timber supports painted (paperbark)
Front view of house from right side.
Downpipes can be seen in this pic. Colour is a little darker than our gutters.
Front view from left hand side.
Front door is now stained and looks much better.
Internal wall and cornice/architrave colours
Internal wall and cornice/architrave colours
Small issue with the paint job (taken as evidence)
This week we are expecting electricians and plumbers to be on site. They will fit off switches, taps, toilets etc.